Tuesday 27 November 2018

Interserve faces £64m claim for Glasgow waste facility completion

Waste company Viridor has revealed it expects to receive at least £64m from Interserve for remedial works and completion of its Glasgow recycling and renewable energy facility.

Viridor parent water company Pennon this morning revealed that the facility and two others at Beddington and Dunbar were all now processing waste with operations due to ramp up over the next 18 months.

It warned that completion of construction of the Glasgow Recycling and Renewable Energy Centre had required a higher level of remediation and expenditure than predicted.

Interserve had its contract on the job terminated in late 2016 when it was replaced by Doosan Babcock.

“This has been driven by the high level of non-conformances that have required rectification for work performed by our previous engineering, procurement and construction contractor.

“Viridor is contractually entitled to recover incremental costs from Interserve, under certain circumstances.  Discussions with Interserve are ongoing with regard to the contractual settlement.”

In addition to contractual recoveries in respect of Glasgow Recycling and Renewable Energy Centre there were further possible recoveries that were contingent on events in the future.



from Construction Enquirer http://www.constructionenquirer.com/2018/11/27/interserve-faces-64m-claim-for-glasgow-waste-facility-completion/

via Tumblr http://ndbasilica.tumblr.com/post/180546149719

No comments:

Post a Comment