Friday, 31 March 2017

Further delays hit £335m Carillion hospital job in Liverpool

The opening of Carillion’s £335m Royal Liverpool University Hospital job has been delayed again following construction problems.

Work on the site was temporarily halted in January when cracks were found in two concrete transfer beams

Work was running six months late with a scheduled completion time of June.

But the Liverpool Echo said health chiefs at the Royal Liverpool and Broadgreen University Hospitals NHS Trust are now resigned to construction work stretching to next February and moving in next summer.

A Carillion spokesperson said: “We are disappointed that the opening of the new Royal Liverpool Hospital has been delayed.

“The construction of such a building on a brownfield city centre location is a very complex process and we have encountered some issues which have unfortunately led to a delay in the handover date to the Trust.

“We continue to work closely with the Trust to ensure that we handover the building as soon as possible in order for the transition into the new hospital to start.”



from Construction Enquirer http://www.constructionenquirer.com/2017/03/31/further-delays-hit-335m-carillion-hospital-job-in-liverpool/

via Tumblr http://ndbasilica.tumblr.com/post/159030527549