Tuesday, 11 September 2018

Aberdeen bypass woes almost over for Galliford Try

The Aberdeen bypass job dragged Galliford Try’s construction division down to a £29.1m operating loss for the year to June 30 2018.

But the firm highlighted a “strong underlying performance” from construction outside of the latest £45m hit from the Aberdeen Western Peripheral Route.

The numbers were also lowered by “some continuing costs from legacy projects, and the absorption of circa £8.0m of defects claims.”

Pre-exceptional costs construction made a £15.9m profit – up from a £900,000 loss last time on turnover up to £1,687m from £1,569m.

Those number saw construction margins hit 0.9%.

The total hit for AWPR has been £123m but Galliford said: “The majority of the route is now complete with significant sections open to the public, and completion of the remaining bridge expected in late Autumn.

“Our provisioning for the loss on this project reflects our current estimate of the final costs, and is reduced by an estimate of our share of significant claims against the client and others, which are yet to be agreed and concluded.

“This inherent uncertainty will be resolved only when the project is complete and the claims finally settled.

“We have continued to enhance our project approval process, ensuring we only take on projects with appropriate levels of risk and anticipated profit.  The portfolio of newer work is performing well and delivering appropriate margins that reflect the associated risk profile.”

Another strong year at Linden Homes helped group pre-tax profits increase to £143.7m from £58.7m on revenue up to £3,132m from £2,820m.

Linden made an operating profit of £184.4m at a margin of 19.5%.

Peter Truscott, Chief Executive, said: “Linden Homes continued to prioritise margin growth, benefiting from further standardisation and the robust control of overheads.

“The underlying Construction business performed well and continues to see a pipeline of suitable opportunities, with new projects delivering improved margins.

“We have made good progress towards completion of the AWPR contract, with significant sections of the road open to traffic and the final section expected to be open by late Autumn 2018.”



from Construction Enquirer http://www.constructionenquirer.com/2018/09/12/aberdeen-bypass-woes-almost-over-for-galliford-try/

via Tumblr http://ndbasilica.tumblr.com/post/178000705599

No comments:

Post a Comment